PROPERTY
Suite Size | 2,000 SF |
Year Built | 1971 |
Property Type | Flex |
Location | South Central Omaha Industrial Submarket |
PROJECT DETAILS
Start Date | March 1, 2020 |
End Date | September 25, 2020 |
Spaces | 5 Offices Conference Room Kitchen Bathroom Lobby |
PROJECT HIGHLIGHTS
- Masonry window was added to north side. Significant engineering was required to support concrete roof deck.
- Kitchen footprint and conference room size were increased by moving west walls.
- New LED lighting added a modern look while increasing efficiency for tenants.
- Motion sensors were added to offices.
- Added interior windows allowing outside light into back spaces.
MAJOR POINTS
- Designer was brought in for minimal time and cost which maximized the return on paint, trim, and carpet changes.
- COVID-19 and masonry challenges slowed the process of the project, but Investors’ relationships with contractors helped the project keep moving.
- Space was leased before the project was completed. Tenants were able to see the quality and final finishes before the space was finalized.
Jason Velinsky
Director of Project Management
402.769.7581
jvelinsky@investorsomaha.com